2021-09-23
2021 is the start of “The 14th Five-year Plan”.Annec still working on his target“Continuously Promote R&D of HBS Technology an Progress in Refractory.”.We got 13 HBSs projects and 75K Tons refractory materials in Jan and Feb, and then got 5 HBSs projects in Mar. All 10 HBS sites also processing in these times as the plan. This is a good start of ANNEC. Also is good beginning of the work in 2021.
In 01st.Mar.2021, ANNEC got a bid from Linyi Steel. The EPC of this Project is MCC, the partner of ANNEC. ANNEC supply the design for 4 HBSs and 15k Tons refractory materials in this order.
In 07th.Mar.2021, The shell of 1#HBS in 3# Furnace of ZENITH had successfully capped. The next step is constructed the refractory bricks. The EPC of this project is CISDI Group, This project including 12 HBSs of 3 Furnaces with 2400m³volume. All the refractory materials in total 43k Tons are supplied by ANNEC. Total 8 HBSs in 2# and 3# furnace use the Technology from ANNEC.
In 10th Mar 2021, Phase II Construction Project of KISC had capped. The body of the HBS had begun already. The next work is constructing the refractory bricks. ANNEC supply the technology and 13k Tons materials to one HBS with 2500m³ volume.
In 13th Mar 2021, 4 HBSs of 1# furnace in Great Dong Hai Corporation project capped. This project have 2 site HBSs in 1260 volume. The EPC and the refractory materials 24k tons are supplied by ANNEC.
In 14th Mar 2021, ANNEC got the HBSs upgrade project of 4# furnace in Xinyang Steel. ANNEC supplied refractories more than 2000 tons.